170th Avenue (FY 2020-22 Pedestrian Improvement)

Project Timeline

Estimated completion date: 08/31/2022

 

Note: Project dates are estimates and subject to change

  • Preliminary design: through December 2020
  • Right-of-way acquisition: March-November 2021
  • Final design: May 1, 2021
  • Contractor bid process: January-February 2022
  • Start of construction: March 2022
  • Project completion: August 2022