Basalt Creek Parkway Extension

Current Activity - design

 

Project Updates 2/19/2021: Project team will present a project update to the Tualatin City Council on Feb. 22, introducing the road project to new council members.

 

Past Updates

Project Updates 10/30/2020: Updated exhibits and an FAQ are now available.

 

Project Updates 8/17/2020: The Basalt Creek Extension has progressed towards at 30% desgin level. View letter

 

Project Update 4/15/2020: The proposed bicycle and pedestrian design has been updated. View letter

 

Project Update 1/9/2020: An open house summary now available in the Design section of this page.

 

Project Update 10/29/2019: Exhibits from the Oct. 23 open house are now available in the Design section of this page.

 

Project Update 6/10/2019: Open house exhibits are now available in the Design section of this page. Please send comments to lutproj@co.washington.or.us.

 

Project Update 5/29/2019: An open house is 5-7 p.m. at Ibach Park, 10455 SW Ibach St. Media release

 

Project Update 1/18/2019: Consultant has been contracted; design survey will begin this winter.