Century Boulevard/TV Highway Intersection

Current Activity - design

 

Activity Update 3/8/2021: Construction is delayed until summer due to issues with permits and agreements. Update road closure and detour information will be available before construction.

 

 

Prior updates


Activity Update 11/15/2019: This project is now in final design and right-of-way acquisition. Construction is now anticipated May 1, 2020-Oct. 1, 2021.

 

Activity Update 8/9/2019: Construction will be delayed by six to nine months due to circumstances beyond the control of Washington County. A new permitting approval process has been implemented for work in the railroad right-of-way, which will be completed as quickly as possible.

 

Activity Update 5/30/2019: Two road closures are required for this project.

  • August-January: Century Boulevard, between Tualatin Valley Highway and the Goodwill driveway, will be closed to vehicle traffic. Pedestrian traffic will be maintained, except during three weeks of railroad work anticipated for November-December. Detour map
  • January-March: Century Boulevard, south of Alexander Street, will be closed to vehicle traffic. Pedestrian traffic will be maintained. Detour map

An open house is 5-7 p.m. June 13 at Century High School, 2000 SE Century Blvd.

 

Activity Update 2/27/2019: Construction is tentatively scheduled to begin June 1 with completion by Oct. 1, 2020.