Filbert Street (FY 2020-22 Pedestrian Improvement)
Project Timeline
Construction start date: 09/01/2021Estimated completion date: 12/31/2021
Note: Project dates are estimates and subject to change
- Survey and studies: April-October 2020
- Preliminary design: Through January 2021
- Final design: January-April 2021
- Right-of-way acquisition discussions: February-July 2021
- Contractor bid process: July-August 2021
- Start of construction: September 2021
- Project completion: December 2021