Tualatin-Sherwood Road (Highway 99W Crossing)

Current Activity - design

 

Update 3/8/2021: Project design is complete. Right-of-way acquisition is in progress. Construction contract bid dates to be determined in coordination with Willamette Water Supply. A summer construction kickoff open house is planned.

 

Prior Updates
_________________________________

Activity update 11/15/2019: Final design and right-of-way acquisition continues. Construction is now anticipated for April 1, 2021-Oct. 1, 2024.

 

Activity update 2/15/2019: Project has entered the final phase of design; right-of-way acquisition has begun

 

Activity update 1/7/2014: This project is currently on hold due to a Land Use Board of Appeals (LUBA) appeal. Final design and construction will commence upon resolution of the appeal.