Tualatin-Sherwood Road (Teton Avenue to Langer Farms Parkway)
Project Description
This project will widen Tualatin-Sherwood Road, between Teton Avenue and Langer Farms Parkway, including:
- Five travel lanes (two travel lanes in each direction and a center turn lane).
- Bicycle and pedestrian facilities on both sides of the road.
- Storm drainage facility upgrades.
- Street lighting.
The Tualatin Sherwood Road project is being done coordinating with the Willamette Water Supply Program pipeline installation. The WWSP, a partnership between Tualatin Valley Water District and the city of Hillsboro to build an additional regional water supply system in Washington County, will be constructing a 66-inch drinking water pipeline in conjunction with the roadway improvements.
Funding Information
This $31.5 million project is funded through the County's Major Streets Transportation Improvement Program (MSTIP 3e). Total estimated project cost includes design, right-of-way and construction, and is subject to change.